This is our land after we had cleared trees and brush up to my head in several places.

These bulldozers made short work of clearing our land in the first phase of our building program.

There was at least six dump truck loads of concrete, dirt and vegitation to clear from our land.

This was our crew plotting out the exact points where the corners of the house/church should be. They have to be exact because the building can't be any closer to the boundaries of the land than 3 meters according to the law.

This large hole in the ground is called a katlavan. The foundation had to be at least 1.3 meters below the ground because soil in our area any higher than that freezes and then thaws, cracking foundations. There is a significant incline to the land so at the beginning our foundation in some places was 2.4 meters below the ground and in others only 1.5. We would level out the land further to make it more even around most of the building.

It took dump truck after dump truck to take away all this earth.

This was what we put on the floor of the hole. It is a large footing for the concrete walls of the foundation that will be made by those large blocks you see in the middle.

The concrete footing is one complete mass, all poured at the same time, reinforced with five pieces of rebar along the length, and many short pieces of rebar crossing that to form a net effect. Every foundation "sits" a little bit, in other words it sinks into the ground just a bit. The important thing here, is to make sure that the whole house "sits" the same, and not one side more than the other.

Each one these blocks had to be lifted into place by the large crane you see pictured here. In all there were 216 blocks that needed to be placed.

This is what the blocks looked like when they were finished. We then leveled out the land further to make it mostly even with these walls so that we would not have a problem with freezing.

Here you can see a little of the scope of the project. The great thing about having this basement space is that in the future it could come in very handy for an expanding church family.

In the background you can see people laying bricks, this will provide for some head room in the basement making the space useable and also help the floor to be exactly level.

Here the brick layer is mostly done and ventilation tubes have been installed to help with the moisture that can accumulate.

These concrete panels also need a crane to lift them into place. They are prefabricated with lots of rebar and are built so that they can support a great deal of weight only sitting on a couple of centimeters of foundation at their tips.Each one of these panels can support 800 kg (1763 lbs) of weight for every square meter of area. I guess I can eat as much fudge as I want now with no worries.

The entire foundation is now covered with tiles, and there has been installed a little concrete staircase to the garage as well. It will sit fine until we can begin working again on it in the spring. Praise the Lord for this progress. Thank you to all of those who pray and sacrifice to make these things possible.

 
 

Home | Family | Ministries | Updates | Resources | Contact | Heaven?

©2004 Adam Young Ministries Lancaster Baptist Churchadamyoung@theyoungs2russia.org